TDA No. CDV23-0362 / JM No. 24134

City of West Tawakoni – 2023 CDBG WTP Improvements – CID 03 – Pumps and Filter Install

Project Description

 

PROJECT INCLUDES:         The proposed project includes installing two new 1,000 gpm raw water pumps at the existing headworks station, and installing piping, valves and media to bring filter #4 online.

ESTIMATED COST:             $ 300,800.00

BID BOND:                           5%

PERFORMANCE/PAYMENT BONDS:      100%

FUNDING AGENCY:           Texas Department of Agriculture / TDA No. CDV23-0362

Contractors: Please note that we have a new feature on our website. Questions should now be entered online, in the box provided for each project prior to the question deadline. To avoid duplicating questions, please review the previously submitted questions posted at the bottom of each project’s web page.

Questions will be automatically directed to and reviewed by the project manager. All project specific questions posted here will be answered via addendum and distributed to all plan holders. Addenda will also be posted to the website and may be accessed by clicking the red “Addendums” button.

Contractors must obtain a set of CONTRACT DOCUMENTS online at www.jacobmartin.com by digital download or hard copy to be considered a registered plan holder eligible to bid the project. Cost for digital download of CONTRACT DOCUMENTS will be $0.00.  Hard copies of the CONTRACT DOCUMENTS will be $100.00  All Copies of the CONTRACT DOCUMENTS must be ordered online and are available for pick up, mail out or digital download via www.jacobmartin.com.  Upon verification of online payment, hard copies may be picked up at Jacob & Martin, LLC, located at 1925 Fort Worth Highway, Weatherford, Texas 76086.

The project to be constructed will be financed with assistance from the Texas Department of Agriculture (TDA) under the U.S. Department of Housing and Urban Development Community Development Block Grant (CDBG) program and is subject to all applicable Federal and State laws and regulations. Attention is called to the fact that not less than, the federally determined prevailing (Davis-Bacon and Related Acts) wage rate, as issued by the Texas Department of Agriculture Office of Rural Affairs and contained in the contract documents, must be paid on this project. In addition, the successful bidder must ensure that employees and applicants for employment are not discriminated against because of race, color, religion, sex, sexual identity, gender identity, or national origin.

All contractors/subcontractors that are that are debarred, suspended, or otherwise excluded from or ineligible for participation on federal assistance programs may not undertake any activity in part or in full under this project.

The lobbying certification must be submitted with the bid packet to be considered complete and responsive.

The City of West Tawakoni is an Equal Opportunity Employer.

Project Details

  • Project No: TDA No. CDV23-0362 / JM No. 24134
  • Owner: City of West Tawakoni
  • JM Office: Weatherford
  • Project Manager: Nic Kirk, P.E. / nkirk@jacobmartin.com
  • Admin Contact: Trish Cassaday / tcassaday@jacobmartin.com
  • Phone: (817) 594-9880
  • Prebid: No Prebid
  • Prebid Date: N/A
  • Bid Open Date: February 18, 2025 at 1:00 PM at West Tawakoni City Hall, 1533 TX-276, West Tawakoni, TX 75474

Select Plan Type:

Planholders List

First Name Last Name Company Email Phone Contractor Role
MattYbarraMPImatthew.ybarra@mcwanepi.com9035301391Supplier
KaciMayfieldCoburns Supplykmayfield@coburns.com5807475789Supplier
ChaseCunninghamFerguson Waterworkschase.cunningham@ferguson.com9039412328Supplier
KevinStrykerStryker Electric, LLCkevinstrykerelectric@gmail.com9038522060Sub Contractor
CaymenRossCore & Maincaymen.ross@coreandmain.com19039412290Supplier
KevinClementH&H Electrical Contractors, Inc.kevinc@hhelectrical.biz9725240205Sub Contractor
ShannonLackeyKopathean Electric, LLCshannon@kopathean.com8306135923Sub Contractor
CarleyCampElliott Electric Supplycarleycamp@elliottelectric.com4699131945Supplier
JefferyMartinDealers Electrical Supplyjeff@jefferykmartin.com9033533974Supplier
MattPetersonA&V Watermatt@estacadointerests.com2145465685General Contractor
ChrisDormanUnderground Utility SupplyHal@undergroundutilitysupply.com9037878840Supplier
JasonMcNattPierce Pump Companyjmcnatt@piercepumpco.com4695159890Supplier
KenKochambaOdessa Pumpsken.kochamba@dnow.com9725221296Supplier
AnthonyMayesGDC Industrial Inc.anthonymayes@groupgdc.com9032430526General Contractor
GeraldDowningDowtech Specialty Contractors, Inc.dowtech@dowtechspecialty.com3258934684General Contractor
ErinCreedKore Systems, Incadmin@koresystems.net8773939906Sub Contractor
ChadLappinSuperior Equipment Solutions LLCsuperiorequipment23@gmail.com19035883250General Contractor
EricFieldsEnvironmental Improvements, Inc.mledger@ei2water.com9724362536Supplier
PlanAquisitionConstruct Connectcontent@constructconnect.com8003642059Plan Room
JackTreadwellSummit Solutions, Inc.jack@summitsolutionsus.com6782837355General Contractor
DANNYJOHNSONGDC INDUSTRIALdannyjohnson@groupgdc.com9032430428General Contractor
BrettGartnerExpanse Electricalbrett.gartner@expanseelectrical.com7203200722Sub Contractor
TJMcKinneyMcKinney and Moore of Texas, LLCtj@mckinneyandmoore.com9033603655General Contractor
BrianTroutAxis Water Technologiesbrian.trout@axiswater.com4325286656Sub Contractor
MarcCashionGlobal Pump Solutionsmarc@gpspumps.com8172407728Supplier
KyleNelsonRangelinekyle@rangeline.com8172398536Sub Contractor
GeorgiaGoodRLC Controls, Inc.georgia@rlccontrols.com5129666366Sub Contractor
MaryMillerPWXPressbids@pwxpress.com4086768941General Contractor
CODYHAMBLINLeonard Water Servicescolin@leonardwaterservices.com3256691903General Contractor
BryanWeemesXylem, Inc. (Flygt Products)bryan.weemes@xylem.com2149529301Supplier
RandyKeyZone Industriesrkey@zoneindustires.com8179125151Supplier

Questions

Company Name Question
GDC Industrial Inc. Anthony Mayes On Proposed Pump Site Alternate Sheet 06- "Proposed Headworks Site"- Will the existing 6" WL to clarifiers be abandoned in place or will this require demo to allow installation of the 80LF of 8"?
Odessa Pumps Ken Kochamba Section 11 05 03 VTP's - Drawings on Sheet 05 - 08 - Can you please provide more detail on the pump mounting elevation (or discharge pipe elevation) and bottom of wet well elevation, to determine total pump length.