City of Ropesville – Water Treatment Improvements – Contract 2: Ground Storage Tank

Project Description

 

A non-mandatory Pre-Bid Conference will be held via Zoom Meeting (information below), at 2:00 PM on July 15, 2026, to discuss the scope of the project and answer any questions prospective bidders may have concerning specifics of the project. The Contractor or his designated representative may attend.

-------------------------------------------------------------------------------------------

Topic: Non-mandatory Pre-bid Meeting for Ropesville

Time: Jul 15, 2026 02:00 PM Central Time (US and Canada)

Join Zoom Meeting

https://jacobmartin.zoom.us/j/87021581034

Meeting chat link

https://jacobmartin.zoom.us/launch/jc/87021581034

Meeting ID: 870 2158 1034

---

One tap mobile

+15642172000,,87021581034# US

+16469313860,,87021581034# US

---

Join by SIP

Join instructions

https://jacobmartin.zoom.us/meetings/87021581034/invitations?signature=mM9F8Tr9oksdP6Ouau2e2yoh7TrS0TGA47Yq5j5Zdfo

-------------------------------------------------------------------------------------------

PROJECT INCLUDES:                    The installation of a 60,000 gallon welded steel ground storage tank.

ESTIMATED COST:                         $250,000

BID BOND:                                                    5 %

PERFORMANCE/PAYMENT BONDS:         100 %

FUNDING AGENCY:                        Texas Water Development Board (TWDB) / TWDB No. 62863

Contractors: Please note that we have a new feature on our website. Questions should now be entered online, in the box provided for each project prior to the question deadline. To avoid duplicating questions, please review the previously submitted questions posted at the bottom of each project’s web page.

Questions will be automatically directed to and reviewed by the project manager. All project specific questions posted here will be answered via addendum and distributed to all plan holders. Addenda will also be posted to the website and may be accessed by clicking the red “Addendums” button.

Copies of the CONTRACT DOCUMENTS must be ordered online at www.jacobmartin.com.  Orders for CONTRACT DOCUMENTS may include hard copies for pick up, mail out or digital download via www.jacobmartin.com.  Upon verification of online payment, hard copies may be picked up at Jacob & Martin, LLC., located at 3465 Curry Lane, Abilene, TX 79606.  Cost for hard copies of the CONTRACT DOCUMENTS will be $100.00.  Cost for digital download of CONTRACT DOCUMENTS will be $0.00.  Contractors must purchase a set of CONTRACT DOCUMENTS to be considered a registered plan holder eligible to bid the project.

A certified check or bank draft, payable to the order of City of Ropesville, negotiable U.S. Government bonds (at par value) or a satisfactory Bid Bond executed by the Bidder and an acceptable surety in an amount equal to five percent (5%) of the total bid (Water Code 17.183) shall be submitted with each bid. The Contractor shall utilize a surety company which is authorized to do business in Texas in accordance with Surety Bonds and Related Instruments, Chapter 3503 of the Insurance Code.

This contract is contingent upon release of funds from the Texas Water Development Board (TWDB).

Any contract(s) awarded under this Invitation for Bid (IFB), Request for Proposals (RFP), or Request for Qualifications (RFQ) is/are expected to be funded in part by financial assistance from the TWDB. Neither the U.S. Environmental Protection Agency (EPA) or the State of Texas, nor any of its departments, agencies, or employees, are or will be a party to this IFB, RFP, RFQ, or any resulting contract.

The Owner reserves the right to waive any informalities and to reject any or all bids.

For SRF Equivalency projects approved under the 2022 IUP or earlier –Any contract(s) awarded under this Invitation for Bids is/are subject to the American Iron and Steel (AIS) requirements of federal law, including federal appropriation acts and/or Section 608 of the Federal Water Pollution Control Act.

Equal Opportunity in Employment - All qualified Applicants will receive consideration for employment.

Davis-Bacon prevailing wage rates are applicable. Davis-Bacon prevailing wage requirements apply to the construction, alteration or repair of treatment works carried out, in whole or in part, with assistance made available by the Clean Water State Revolving Fund (CWSRF) or a construction project financed, in whole or in part, from the Drinking Water State Revolving Fund (DWSRF).

For additional information on Davis-Bacon Wage Rate Requirements and its applicability to this contract, please consult TWDB Guidance No. DB-0156.

 

Project Details

  • Project No: TWDB No. 62863 / JM No. 19119
  • Owner: City of Ropesville
  • JM Office: Lubbock
  • Project Manager: Allen Phillips, P.E. / aphillips@jacobmartin.com
  • Admin Contact: Katy Stryker / kstryker@jacobmartin.com
  • Phone: (806) 368-6375
  • Prebid: Non-Mandatory
  • Prebid Date: July 15, 2026 @ 2:00 PM via Zoom
  • Bid Open Date: July 30, 2026 at 2:00 PM at City Hall, 107 Hockley Main St., Ropesville, TX 79358

Select Plan Type:

Planholders List

First Name Last Name Company Email Phone Contractor Role
GeraldPompaHartwell Environmentalgpompa@hartwellenv.com(512) 350-1398Supplier
CharlesSchniedersCummins Sales and Servicecharlie.a.schnieders@cummins.com(214) 676-0179Supplier
ScottWamplerScott Wampler Construction ServicesBids@swcstexas.com18063364694General Contractor
LaneSalvatoThe Barry Group, LLC Independent Representative of Tnemec Company, Inc.lsalvato@barrygroupllc.com(972) 312-8448Supplier
Marymillerpwxpressbids@pwxpress.com4086768941Plan Room
Marymillerpwxpressbids@pwxpress.com4086768941Plan Room
CourtneySledgeRaider Fence, LLCinfo@raiderfence.com+18066208880Sub Contractor
JackieHowardL. Howard Construction, Inc.lh_estimating@windstream.net8068325018General Contractor
TroyLacobeeNewman Regency Grouptroy@newmanregency.com18172642713Supplier
ChristopherEustaceEverSolve Technologiesceustace@goeversolve.com18064965000Sub Contractor
GeneJones, Jr.Maguire Iron, Inc.bidreports@maguirewater.com6053349749General Contractor
ShawnEllisFrietze Industrial Service Technicianselliss@fist.llc(806 )842-3592Sub Contractor
DavidDuffeeIndependent ElectricDavid@ind-elec.com8065493707Sub Contractor
VictorRanawatTaknekvictor.ranawat@taknek.com9406411041General Contractor
EdithHallPaso Robles Tank, Inc.hemetreception@pasoroblestank.com9519255022Sub Contractor
PollyVannV-tech Environmental Servicesinfo@v-teches.com(806) 748-1700Sub Contractor
TylerBeltPioneer Supplytbelt@pioneersupplyok.com14057947705Supplier
DaynanColemanTitan Environmental USAd.coleman@titanenviro.com3465878621Sub Contractor
DanielIzzardBrown-McKee, Inc.danieli@brownmckee.com8067454511General Contractor
ElEstrabelaConstructConnectEl.Estrabela@constructconnect.com2402219248Plan Room
DavidBrackneyRiley Industrial Services, Inc.estimating@rileyindustrial.com5053274947Sub Contractor
LaneSalvatoThe Barry Group, LLC Independent Representative of Tnemec Company, Inc.lsalvato@barrygroupllc.com(972) 312-8448Supplier
ChrisKeslerTurkey Creekckesler@tcreek.com806-679-7123General Contractor
ShannonLackeyKopathean Electric, LLCshannon@kopathean.com8306135923Sub Contractor
MichaelCarpenterEnvironmental Improvements, Inc.mledger@ei2water.com9724362536Supplier
TaylorKennedyCurtis Service Companytkennedy@curtisserviceco.com+18066627052General Contractor
Marymillerpwxpressbids@pwxpress.com4086768941Plan Room
VenkateshSivaBlackridge Research & consultingvenkatesh@blackridgeresearch.com(917) 993-7467Plan Room
GeraldDowningDowtech Specialty Contractors, Inc.dowtech@dowtechspecialty.com3258934684General Contractor
GeraldDowningDowtech Specialty Contractors, Inc.dowtech@dowtechspecialty.com3258934684General Contractor
ConnorHoelscherTexas Water and Soil Company, Inc.connor@texaswaterandsoil.com3256569813General Contractor
GeraldDowningDowtech Specialty Contractors, Inc.dowtech@dowtechspecialty.com3258934684General Contractor
JoshFLudDeerWood ConstructionJflud@deerwoodinc.com18063921975General Contractor
WilliamBarnettBenmark Supplywilliambarnett@benmark.com3256929889Supplier
DarrylHarrisTank & Vessel Builders, LPkseago@tankandvesselbuilders.com(325) 854-8450General Contractor
TressieMooreBulldog Steel Products, Inc.tressie@bulldogsteel.com3258935806General Contractor
SARAHKELLYAmtek USAamtek.austin@amtekusa.com2813764577Plan Room

Questions

Company Name Question
D&R Tank Company Jake Hawkins 1. Drawing C-6 shows cages at the exterior ladders. Cages are no longer acceptable by OSHA for fall protection. A safety climb system is recommended. To prevent unauthorized access, a locking ladder gate can be provided. Please verify if a cage will be required in addition to a safety climb system. 2. Drawing C-6 shows iron pipe for the tank overflow with welded supports to the steel tank. To avoid corrosion issues from using dissimilar metals, is a welded steel pipe acceptable for the overflow? 3. Drawing C-6 shows a 4” drain nozzle located 2” clear above finished floor. API 650 states a 4” standard shell nozzle to be located 8” clear distance above finished floor elevation. Please confirm if this is acceptable? 4. Drawing C-6 shows a 4” drain nozzle located 2” clear above finished floor. API 650 states a 4” standard shell nozzle to be located 8” clear distance above finished floor elevation. Please confirm if this is acceptable? 5. Drawing C-6 shows a 4” drain nozzle located 2” clear above finished floor. API 650 states a 6” standard shell nozzle to be located 8 13/16” clear distance above finished floor elevation. Please confirm if this is acceptable? 6. Has a geotechnical investigation been completed for this site? If so, can the resulting report be provided for use in the design of the tank foundation? 7. What is the Davis-Bacon Wage decision number?